In a ruling dated 5 December 2024 (Civ. 3rd, No. 22-20.708), the Court of Cassation confirmed a broad interpretation of the seller’s obligation to deliver in accordance with the contract, holding that the classification of ‘access road’ could imply a legitimate expectation that it would be developed into a carriageway.